Schedule Estimating Threshold

Project SchedulingWhen you create a schedule you generally don’t know enough to enter all of the detailed activities the first time though. Instead, you identify large chunks of work first, and then break the larger chunks into smaller pieces. These smaller pieces are, in turn, broken down into still smaller and more discrete activities. This technique is referred to as creating a Work Breakdown Structure (WBS).

A question people ask is how small the activities should be before they do not need to be broken down further. This is referred to as your “estimating threshold”. Work can be broken down into smaller activities than the estimating threshold, but normally no work would be left at a higher level. The threshold can be different based on the size of your project and how well the work is understood.

You can use the following criteria as a guide. For a typical large project (say 5000 effort hours or more) the activities should be no longer than two weeks. Medium and small projects (say 1000 effort hours or less) should have activities no larger than one week. Remember that this threshold is an upper limit. You can break the activities down further if you want.

Assigning work that is smaller than your threshold allows the work to be more manageable. Think about it. When you assign work to a team member you don’t know for sure how he is progressing until the due date (or the completion date if it comes first). (Yes, you can track progress if the work proceeds linearly – like painting a wall. But many of us work in the knowledge business (IT, Sales, Finance) and it is not easy to know exactly how the work is progressing.)

Let’s look at an example. If you assign a team member work that is due in four weeks, you are not going to know for sure whether the work is on time until the four-week deadline. The worker may tell you things are on track, but you don’t really know for sure until the due date. If the work is completed you will know you are on track. If the work is late you will know it then as well. However, four weeks (or longer) is too long to wait to know if the work is on track. A better approach is to break the four-week activity into four one-week activities. Then you will know after the first week if the work is on time or not.

If at all possible you want to try to have schedule work completed within two weeks. If you give someone work that takes four weeks or longer there is just too much time before you really know if things are on-track or not. It is much better for you if you can keep the schedule feedback loop to no more than two weeks.